Expedited schedule delivers critical project within budget.
Thibodaux Regional Health System negotiated with DonahueFavret to build a 10,000 SF operating room expansion on a fast-tracked schedule. The peconstruction services were completed in roughly six months and the construction will be expedited to finish in just over eight months. The preconstruction process allowed the team to preorder long lead materials such as steel MEP equipment and also keep the project within budget by working collaboratively with the design team.
The project includes four operating rooms and a mechanical penthouse. The addition abuts existing operating rooms which are in operation throughout construction. The steel-structured building includes an elevated crawl space and timber piles. The project also includes all new MEP infrastructure to support the new OR rooms.

Square Footage
10,000
Completion
8 months (2022)
Owner
Thibodaux Regional Health System
Architect
Project Location
Thibodaux, LA